News · Garden Route · Waste infrastructure · Public accountability
Garden Route waste facility reaches 90%, but construction is only part of the test
The district's latest update reports 90% completion of phase one near Mossel Bay. Remaining work and operating approvals still matter before waste disposal begins.

Phase one of the Garden Route District Municipality's regional waste facility is 90% complete, according to its 2 November progress update. For residents following a major public project, the next question is what must happen before that construction becomes an operating service.
The facility is approximately 15 kilometres outside Mossel Bay, beside PetroSA. The latest report identifies the leachate and contaminated-water dams as critical outstanding work and puts them at 81% complete.
Rain delayed the final concrete work
District waste-management manager Johan Gie said recent rain had delayed pouring concrete into the final geocell layer. Work originally expected to finish by the end of October was then expected within two weeks of the update. The municipality nevertheless said the contractor remained on programme.
Other remaining tasks include finishing buildings, marking access roads, stone pitching at stormwater headwalls and shaping the site. That timetable is an expectation recorded on 2 November, not confirmation that the work has subsequently finished.
The earlier report set an approvals condition
The previous update, headed 12 October, put overall phase-one construction at about 82%. It said Cell 1A was 99% complete and described multiple dam-lining layers, including a drainage layer for detecting leakage, before the planned concrete-filled geocells.
Crucially, that earlier report said waste disposal could begin only after the necessary approvals, including a positive Record of Decision, had been obtained from the national environmental and water departments. Liner testing and supporting documents were still being completed at the time.
The October update put the dams at 82%, while the November report records 81%. Neither statement explains that difference. The figures can be reported with their dates, but they do not establish a continuous increase in the completion of that particular component.
What residents can look for next
A construction percentage answers how far a reported building programme has advanced. It does not answer whether required approvals have been issued, what testing has demonstrated or when the public service will start.
The next useful milestones are therefore identifiable ones: completion of the remaining works, confirmation of the relevant approvals and a clear operating announcement. Neither of these two updates establishes an opening date. Keeping those milestones separate allows residents to recognise progress while still asking precise questions about delivery.
Read the evidence: GRDM: progress update 7 on the regional waste-management facility (opens in a new tab) · GRDM: progress update 6, headed 12 October 2026 (opens in a new tab)
Sources, evidence and corrections
- GRDM: progress update 7 on the regional waste-management facility (opens in a new tab) · 2 November 2026
- GRDM: progress update 6, headed 12 October 2026 (opens in a new tab) · Update headed 12 October 2026; website publication label 9 October
Source records reviewed on 5 November 2026. Publication dates and reporting periods are shown above.
