Local Government · Nelson Mandela Bay · Housing
At 97, Nomademfu Maggie Noda receives a home in Kariega
A housing handover for an elderly resident comes as Nelson Mandela Bay continues a separate 153-home construction programme.

Nomademfu Maggie Noda, 97, has received a home in Kariega through the PE Destitute Housing Project, according to a Nelson Mandela Bay Municipality update published on 28 October (opens in a new tab).
The municipality’s account records Noda reflecting on experiences reaching back to her youth, and on prayer and faith. Her handover brings an individual life into a public discussion often dominated by budgets and building targets.
In related updates (opens in a new tab), the metro reported Eastern Cape Human Settlements MEC Siphokazi Lusithi’s emphasis on prioritising senior citizens, child-headed households and people living with disabilities. Lusithi also called for provincial and municipal cooperation to overcome delivery obstacles.
Executive Mayor Babalwa Lobishe said the municipality was exploring additional funding to accelerate housing provision, according to the same municipal account.
The constitutional duty extends well beyond any single handover. Section 26 (opens in a new tab) protects the right of access to adequate housing and requires reasonable state measures, within available resources, to realise it progressively. For households awaiting assistance, that right depends on sustained delivery. Each completed home makes that obligation concrete, even as the scale of unmet need demands continued work.
153 homes under construction
A separate building programme provides a measure of the metro’s next commitments. In its 7 October report (opens in a new tab), the municipality said construction of 153 houses in Joe Slovo and KwaNobuhle Area 11 had begun on 1 October.
Joe Slovo accounts for 83 homes and KwaNobuhle Area 11 for 70. The combined budget is R33,303,663, approximately R33.3 million, with completion scheduled for 26 February 2027.
The municipality had requested funding for 800 homes: 500 in Joe Slovo and 300 in KwaNobuhle Area 11. Approval covered 153. Seven small, medium and micro enterprises were appointed, three in Joe Slovo and four in KwaNobuhle.
The report estimated the metro-wide housing backlog at approximately 100,000 units and recorded about 150 informal settlements. That scale of need places each completed home within a much larger task.
Noda’s handover stands on its own; the municipality has not identified her home as part of the 153-house programme. Those developments remain under construction.
Completion and handover in February would turn the funded building work into homes available to their intended beneficiaries.
Sources and further reading
- Nelson Mandela Bay Municipality: Nomademfu Maggie Noda, PE Destitute Housing Project, 28 October 2026 (opens in a new tab)
- Nelson Mandela Bay Municipality: PE Destitute Housing Project updates on provincial and municipal priorities, 28 October 2026 (opens in a new tab)
- Nelson Mandela Bay Municipality: 153 houses in Joe Slovo and KwaNobuhle Area 11, 7 October 2026 (opens in a new tab)
- Constitution of the Republic of South Africa: Section 26, housing (opens in a new tab)
